The things that must happen between signing and completion before either party is obliged to complete. Each one is a date in the timetable and a point at which the deal can fail.

Deal terms
Category
16 November 2026
Updated

In one sentence

The things that must happen between signing and completion before either party is obliged to complete. Each one is a date in the timetable and a point at which the deal can fail.

What it is

Most private mid-market deals sign and complete on the same day, and have no conditions at all. Where something must happen first, the agreement is signed, the parties are bound, and completion is deferred until the conditions are satisfied.

That gap is where deals die.

The usual conditions

Regulatory

  • Merger control clearance, where a notification threshold is met
  • Foreign investment screening, which turns on sector and acquirer nationality rather than size, and is now the longest pole in most cross-border timetables
  • Sector approvals: financial services, defence, healthcare, communications

In the UK, a notifiable acquisition under the National Security and Investment Act 2021 that completes without the Secretary of State’s approval is void.1 No drafting waives that.

Contractual and corporate

  • Consents under material contracts with change-of-control clauses
  • Landlord consent to assignment
  • Shareholder approval, where the buyer or seller is listed or has a constitutional requirement
  • Release of security and guarantees

Deal-specific

  • A key customer contract renewed or confirmed
  • A reorganisation completed, in a carve-out
  • Financing in place. A condition a seller should resist, since it transfers funding risk entirely

What to negotiate around each one

  • Who is responsible for satisfying it, and to what standard: reasonable endeavours, best endeavours, or an obligation to accept remedies including divestments. The gap between the first and last is enormous.
  • The deadline for filing, not just for clearance. “Promptly” is not a deadline.
  • Who pays the fees and costs.
  • The long-stop date, and whether it extends automatically if a regulator is still deliberating.
  • What happens on failure. Automatic termination, or a right to walk. And whether anything is payable.
  • Interim covenants: how restrictive, and whether ordinary business decisions genuinely need consent.

Common mistakes

  1. Not scoping them at the first meeting. Ask which regimes could apply and who will check. A seller who finds out in diligence has lost control of the timetable.
  2. Agreeing a long-stop date without working backwards from the real regulatory calendar.
  3. Accepting a weak endeavours standard on a condition the buyer controls.
  4. Forgetting the change-of-control clause in the largest customer contract, which puts that customer inside your transaction.

Sources

  1. National Security and Investment Act 2021, “Section 13: Approval of notifiable acquisition”, in force from 4 January 2022. ↩

Frequently asked questions

What are conditions precedent in M&A?

Requirements set out in the purchase agreement that must be satisfied, or waived, before completion can take place. Common examples are merger control or foreign investment clearance, sector regulatory approval, third-party consents under material contracts, shareholder approval, and the absence of a material adverse change.

What is a long-stop date?

The date by which all conditions must be satisfied. If they are not, either party, or sometimes only one, can walk away. It is negotiated to be long enough for the known regulatory timetables and short enough that the seller is not off the market indefinitely.

Can a condition be waived?

It depends on whose benefit it is for. A condition for the buyer's benefit can usually be waived by the buyer alone. Regulatory conditions generally cannot be waived by anyone, because the obligation is statutory rather than contractual.